In February, Leucadia Cyclery owner Jeff Schade hung a six-foot sign on a piece of construction equipment parked about 10 feet from his storefront, and he left it there. According to The Coast News, the tractor near Avocado Street had gone three weeks without starting its engine.
Avocado Street is one of the places where the finished street is supposed to show up first. The City's plan for the Jupiter Street to La Costa Avenue stretch includes a new crosswalk and pedestrian signal at Avocado, roundabouts at Jupiter Street and Moorgate Road, wider sidewalks, bike lanes, benches, bike racks and hundreds of new trees. In its September 17, 2026 status update, the City of Encinitas put completion at "late Fall 2026."
That date covers Segment C only. When Segment C wraps up, Leucadia will have two finished stretches of highway, and the stretch between them will have a design but no money to build it.
Four Segments, One Finished So Far
The Streetscape covers a 2.5-mile corridor. It broke ground in January 2021, and The Coast News, citing state iBank loan documents, puts the total cost at more than $65 million. Crews have been building it in pieces. Here is where each piece stands, listed south to north, as of the City's September update and The Coast News reporting from July 31, 2026:
| Segment | Stretch of North Coast Highway 101 | Status |
|---|---|---|
| A1, South | A Street to Marcheta Street | Design complete, no construction funding |
| A2, North | Marcheta Street to Basil Street | Completed in 2022 |
| B | Basil Street to Jupiter Street | Design complete, no construction funding |
| C | Jupiter Street to La Costa Avenue | Under construction, late fall 2026 target |
Segment A2 got the roadway and sidewalk work and new roadside trees in 2022. In 2023, the city added new striping, a bike lane and median changes from Basil Street all the way north to La Costa Avenue, plus flashing crosswalks at Diana Street and North Court. That 2023 work is what you drive through now between Basil and Jupiter. It changed the paint, but none of the full rebuild you can see taking shape north of Jupiter has reached it.
So when the barricades come down near La Costa, a southbound drive will pass through the newest version of the street, then the 2023 striping from Jupiter to Basil, then the 2022 rebuild below Basil. Segment A1 at the south end is in the same position as B: drawn, not funded.
Why Segment C Took This Long
The north segment is the most expensive piece by a wide margin. The Coast News reports Segment C at an estimated $32 million, about half the project's total, with construction starting in 2024 and an original completion target of summer 2025. The City puts the start in March 2024.
The schedule grew after the City Council approved more drainage work, including a new storm drain system. Director of Engineering Dan Nutter told The Coast News that the change added about a year and a half. That is why the street has been torn up longer than the original timeline suggested. Much of the work is underground: the City reports that all of the 60-inch, 66-inch and 36-inch storm drainpipe is now in.
The target date itself has moved three times since the original plan. Here is the sequence:
- Original plan: summer 2025.
- June 12, 2024: the City Council approved more funding to finish the 60-inch drainage work between Jupiter Street and La Costa Avenue, and the City set a new target of summer 2026.
- July 31, 2026: Nutter told The Coast News he expected Segment C to be finished by October and said the project was only about a month behind, which he called "pretty darn good" for a job this size.
- September 17, 2026: the City's project page changed to "late Fall 2026."
That makes late fall the City's current estimate, and the fourth date the project has had. Nobody has announced an opening date for either roundabout or a ribbon cutting.
What Is Happening on the Street Right Now
The City's September update lists the work still in progress: cleanout boxes, storm drain laterals, inlets, water service laterals and water main between Jupiter Street and La Costa Avenue. On the west side of the highway just south of La Costa, crews are building new curb, gutter, sidewalk, a bus pad, a bus shelter pad and driveways. In practice, the City says to expect traffic control with occasional lane shifts, plus noise, dust, work lighting and large construction vehicles. It also says driveway and business access will stay open.
The trickiest part for regular drivers has been turning around. Leucadia Donut Shoppe owner Tom Chu told The Coast News that many northbound customers have had to keep going to La Costa Avenue to make a U-turn. Stacy Reddell, executive director of the Leucadia 101 Mainstreet Association, said the lack of a closer U-turn has had a significant effect on businesses along the corridor. In August, NBC 7 San Diego reported the same thing from Leucadia Cyclery: customers named the turn and the parking as the reasons they couldn't get to the shop.
The roundabouts at Jupiter and Moorgate are the planned fix for that, since a roundabout lets a driver reverse direction without riding all the way to La Costa. Until they open, the La Costa turnaround is still how it works.
The Businesses Inside the Work Zone
Reddell told The Coast News she surveyed 20 businesses on the corridor, and their sales fell an average of 25% to 40% over the past year. David Shapiro, co-owner of The Leucadian, said he supports the roadway and drainage improvements, but losing street parking has discouraged customers from booking events there. Giuseppe Georgees runs Sip-N-Sea from a walk-up window on the highway, a format that depends on people being able to stop easily.
These are long-running Leucadia businesses: a bike shop, a donut shop, a bar that hosts events, a walk-up window. Leucadia Cyclery moved to 1900 N. Coast Highway 101 in 2024, so it has been running out of its current storefront for most of the Segment C work. The City's project page closes its status update with a short request: "Please support our local Leucadia businesses during construction."
Leucadia's Sunday Moved Inland This Summer
The highway work isn't the only reason Leucadia's routine looks different this year. The Leucadia Farmers Market, run by Leucadia 101 Mainstreet, spent 20 years at Paul Ecke Central Elementary School. It held its last market there on June 7 because of upcoming construction at the school. Neighbors near the new site appealed, the City Council unanimously rejected the appeal on June 17 with some operating conditions attached, and the market reopened at Oak Crest Middle School on June 21, according to The Coast News.
The market now goes by the Leucadia-Encinitas Farmers Market. It runs Sundays from 10 a.m. to 2 p.m. at 675 Balour Drive, just off Encinitas Boulevard. Parking is available at the Encinitas Community Center, at the Rhoades Preschool across the street, and at the Boys and Girls Club near the back entrance. Reddell told The Coast News that traffic flow and parking worked well that first weekend, helped by the Community and Senior Center lot next door.
One link back to the highway made the move with it. Leucadia Cyclery sponsors a free bike valet at the market with tune-ups, and riders get Bike Bucks to spend with vendors. Part of the market's proceeds now goes to the Oak Crest Foundation.
Dates on the Other End of 101
Downtown, along South Coast Highway 101, the fall calendar is going ahead as planned:
- Saturday, October 31, 5 to 8 p.m.: Encinitas Safe Trick-or-Treat on South Coast Highway 101, with businesses open late, music in the Lumberyard Courtyard, and free family arts activities and parking at Pacific View.
- Sunday, November 22, 9 a.m. to 4 p.m.: the Encinitas 101 Holiday Street Fair on Coast Highway 101 downtown.
If the City's late-fall estimate holds, the Holiday Street Fair may be one of the last big weekends before Segment C is done. Then north Leucadia gets its new roundabouts, the Avocado Street signal and its trees, and the half mile or so south of Jupiter waits for funding the city hasn't secured yet.
If you're weighing what the finished street, and the unfunded gap south of it, could mean for a home near the corridor, Louis Alayza can walk you through it block by block. Let's Connect.